Important Announcement From Northeast Generation
Based on current river conditions, weather patterns, rain forecasts, and flow projections from the National Weather Service, I have put together the following table (cfs is cubic feet per second, all flows are shown in cfs):
| Location |
Current Inflow |
Saturday Noon Projection |
| Lillinonah |
8,000 |
12,700 |
| Zoar |
8,100 |
14,500 |
Note that the projected inflow is such that we will be able to begin to refill Lake Lillinonah from the current elevation of 186 feet CL&P datum immediately. It should take about one day to return the water surface elevation to 190 feet, however, we plan on continuing refilling operations over the weekend. The expected increase in rainfall over the weekend will enable us to refill the lake that much faster.
The coincidental timing of the heavy rains with resulting reservoir operations and the requests for annual maintenance drawdowns for Lakes Lillinonah and Zoar has created a need to alter our plans for drawdowns.
The responsibility for safe operations is NGC's, therefore, we will continue to operate to best control the inflow and discharges at our hydroelectric developments until we are certain that we can provide drawdown services for the lakes in a safe and reasonable manner.
Therefore, I have decided to delay the drawdowns by one week for Lakes Lillinonah and Zoar. The new schedule will be as follows, unless weather conditions and abnormal river flows are such that NGC would need to take alternative courses of action:
Lake Lillinonah - The drawdown will begin at approximately 9:00 p.m. on Friday, October 21st, with the lake reaching elevation 190.0 feet, CL&P datum, sometime on Saturday, most likely before noon. We plan to refill the lake on Sunday, October 30th beginning in the evening around 6:00 p.m.
Lake Zoar - The drawdown will begin at approximately 9:00 p.m. on Friday, October 28th, with the lake reaching elevation 98.0 feet, CL&P datum, sometime on Saturday, most likely before noon. We plan to refill the lake on Sunday, November 6th beginning in the evening around 6:00 p.m.
I am requesting that the Lake Authorities make contact with the lakefront property owners to notify them of the change in schedules. If you have any questions or concerns, please get back to me right away.
Thank you.
Bob Gates - Northeast Generation
Posted by Administrator on October 14, 2005 02:47 PM
|
More Announcements
- Lake Lillinonah Family Day BBQ
- Posted On:
July 28, 2008 07:18 PM
- CT DEP Commissioner signs consent order with City of Danbury regarding Danbury Sewer Treatment Plant
- Posted On:
July 28, 2008 01:54 PM
- Governor Rell Proclaims July 20 - 26 CT Lakes Awareness Week
- Posted On:
July 17, 2008 11:13 AM
- Governers Official Lake Awareness Week Statement
- Posted On:
July 17, 2008 10:14 AM
- Lake Water Summer 2008 Water Treatment
- Posted On:
July 7, 2008 11:50 AM
- Hollywood Comes To Lake Lillinonah
- Posted On:
June 11, 2008 01:57 PM
- Spring 2008 Photos
- Posted On:
June 10, 2008 01:56 PM
- Save The Lake Day A Tremendous Success
- Posted On:
June 5, 2008 11:53 AM
- Spring 2008 Newsletter
- Posted On:
May 21, 2008 02:41 PM
- Key Summer 2008 Dates
- Posted On:
April 23, 2008 04:59 PM
- Save the Lake Day 2008 - May 31th!
- Posted On:
April 10, 2008 11:00 AM
- Lake Lillinonah Seasonal Draw Down is scheduled for October 20 to October 28
- Posted On:
September 24, 2007 03:10 PM
- Invitation to FirstLight Power's third quarterly forum on the Shoreline Management Plan
- Posted On:
August 29, 2007 08:49 PM
- Lake Lillinonah Family Day 2007
- Posted On:
July 11, 2007 03:25 PM
- Friends of the Lake, Lake Lillinonah Authority and FirstLight Power Joint Meeting
- Posted On:
July 3, 2007 12:23 PM
- Spring 2007 Newsletter
- Posted On:
April 17, 2007 08:32 AM
- Save The Lake Day 2007
- Posted On:
March 6, 2007 08:44 PM
- Debris Management Plan 2006 Assessment
- Posted On:
March 6, 2007 08:38 PM
- Local Legislators and Political Representatives
- Posted On:
October 5, 2006 02:49 PM
- FOTL Newsletter - 3rd Quarter 2006
- Posted On:
September 19, 2006 05:20 PM
- Lake Lillinonah Maintenance Drawdown
- Posted On:
September 13, 2006 01:33 PM
- GMS 2006 Regatta - September 24, 2006
- Posted On:
September 13, 2006 12:34 PM
- Water Level Notification
- Posted On:
September 1, 2006 12:00 PM
- FOTL Comments to FERC on NGS Shoreline Management Plan
- Posted On:
August 17, 2006 07:27 PM
- Sample Intervene Letters
- Posted On:
August 14, 2006 05:25 PM
- Final Shoreline Management Plan
- Posted On:
July 29, 2006 02:58 PM
- Final SMP Available
- Posted On:
July 27, 2006 06:33 PM
- Northeast Utilities to Sell Competitive Generation Business to Energy Capital Partners
- Posted On:
July 26, 2006 09:06 PM
- Delegation to tackle Lake Lillinonah water level
- Posted On:
July 23, 2006 08:09 PM
- Attorney Genereal Blumenthal's response to the Shoreline Management Proposal.
- Posted On:
July 10, 2006 12:03 PM
- Environmental Impact on Lake Lillinonah if NU Raises the Water Level to the Legal Maximum Height!
- Posted On:
July 10, 2006 11:59 AM
- Will The Lake Rise
- Posted On:
July 8, 2006 06:19 PM
- Northeast Generation just can't get it right
- Posted On:
July 7, 2006 06:18 PM
- Time bomb on the lake
- Posted On:
July 2, 2006 06:16 PM
- SHORELINE MANAGEMENT PUBLIC HEARING - June 27
- Posted On:
June 24, 2006 11:58 AM
- Water Level Alert - June 23, 2006 at 2:45pm
- Posted On:
June 23, 2006 02:51 PM
- WATER LEVEL ALERT - June 23, 2006 10:30am
- Posted On:
June 23, 2006 12:00 PM
- Revised Shoreline Management Plan
- Posted On:
June 22, 2006 12:24 PM
- Save The Lake Day 2006 - Huge Success!
- Posted On:
June 17, 2006 03:31 PM
- Save The Lake Day
- Posted On:
June 10, 2006 01:17 PM
- Shoreline Management Plan Public Forum on June 27th
- Posted On:
June 8, 2006 07:29 PM
- Timely Notice of Changing Lake Levels
- Posted On:
June 3, 2006 02:24 PM
- Lake Lillinonah Spring 06 Newsletter
- Posted On:
May 22, 2006 04:18 PM
- Letter to Governor Rell from FOTL to encourage support of funding for the Clean Water Fund
- Posted On:
May 19, 2006 04:13 PM
- Lake Level Update and More
- Posted On:
May 17, 2006 09:21 AM
- Northeast Generation Services Announces Name the Skimmer Contest
- Posted On:
May 16, 2006 01:56 PM
- Water Level Alert
- Posted On:
May 11, 2006 02:45 PM
- Northeast Generation Services Requests 90-Day Extension For Shoreline Management Plan Filing
- Posted On:
April 19, 2006 08:15 PM
- FOTL's Official Response to FERC Regarding the Northeast Generation Services Shoreline Management Plan
- Posted On:
April 18, 2006 11:41 PM
- Governor M Jodi Rell addresses the Brookfield League of Women Voters on Tuesday, May 16th
- Posted On:
April 10, 2006 02:25 PM
- Debris Management Program Update from Northeast Generation Services
- Posted On:
April 9, 2006 08:30 PM
- Still River Greenway and Waterway Clean-Up Day on May 20th
- Posted On:
March 5, 2006 06:09 PM
- Raising Lake Level
- Posted On:
February 24, 2006 05:15 PM
- Essex Parnership submits Shoreline Management Plan Final Draft - view and see the FOTL Comments
- Posted On:
February 22, 2006 10:35 AM
- EPA and DEP to Update Residents on Rest of River
- Posted On:
February 9, 2006 07:23 PM
- Shoreline Management Plan
- Posted On:
January 26, 2006 09:05 AM
- Bald Eagle Spotted Near Dam
- Posted On:
January 18, 2006 12:15 PM
- Fund shortage stalls Lake Lillinonah cleanup
- Posted On:
November 22, 2005 11:18 AM
- Danbury may boycott Lake Lillinonah forum
- Posted On:
November 14, 2005 12:41 PM
- Letter to Lake Residents from Northeast Generation
- Posted On:
November 11, 2005 10:01 AM
- Shoreline Management Plan (SMP) Workshops
- Posted On:
November 6, 2005 06:07 PM
- Lake Lillinonah Health Report Forum
- Posted On:
November 1, 2005 12:16 PM
- Water Level Alert
- Posted On:
October 20, 2005 04:35 PM
- FOTL Alert - Draw Down On Lake Lillinonah for Service and Maintenance on the dam
- Posted On:
October 19, 2005 12:11 PM
- Recent Rainfall and Flow Conditions Relative to The Housatonic River
- Posted On:
October 15, 2005 06:24 PM
- Important Announcement From Northeast Generation
- Posted On:
October 14, 2005 02:47 PM
- Water Level Lowered
- Posted On:
October 11, 2005 07:42 PM
- FERC approves NEG Debris Management Plan
- Posted On:
September 21, 2005 04:40 PM
- Draw Down On Lake Lillinonah
- Posted On:
September 19, 2005 09:21 AM
- GMS INVITATIONAL CHALLENGE
- Posted On:
September 15, 2005 11:41 AM
- Still River Study
- Posted On:
September 12, 2005 10:37 PM
- Search on for sources of harmful chemicals in Lake Lillinonah
- Posted On:
September 6, 2005 03:18 PM
- Blue-Green Algae
- Posted On:
August 28, 2005 05:19 PM
- New Friends of the Lake Website
- Posted On:
July 26, 2005 11:06 AM
- Friends of the Lake 2nd Anniversary Celebration
- Posted On:
July 25, 2005 05:04 PM
- Happy Birthday Lake Lillinonah!!!
- Posted On:
July 22, 2005 09:14 AM
- Water Quality Progress Report
- Posted On:
July 20, 2005 04:35 PM
- LLA Announce Copper Sulfate Treatment of Lake Lillinonah
- Posted On:
July 19, 2005 12:20 AM
- Northeast Generation Awaiting Approval
- Posted On:
July 17, 2005 10:50 AM
- Lillinonah Debris Draws Complaints
- Posted On:
June 9, 2005 01:56 PM
- Debris Management Plan for the Housatonic Hydroelectric Project
- Posted On:
February 20, 2005 08:18 PM
|